PMP认证考试试题精选(26)
作者:佚名 时间:2003-10-10 08:39 出处:互连网 责编:chinaitpower
              摘要:PMP认证考试试题精选(26)

  241. Of the following, who has the ultimate responsibility for meeting project quality objectives?
  A. Project Engineer
  B. Project Manager
  C. Functional Manager
  D. Quality Assurance Manager
  E. Project Owner
  ANS: B
  
  242. Risk mitigation involves all but which of the following:
  A. developing system standards (policies, procedure, responsibility standards)
  B. obtaining insurance against loss
  C. identification of project risks
  D. performing contingent planning
  E. developing planning alternatives
  ANS: C
  
  243. The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
  A. Payment authorization
  B. Bid cost considerations
  C. Release payment
  D. Back charge
  E. None of the above.
  ANS: D
  
  244. The sequential steps that define the process for successfully completing a project is:
  A. Implementation Plan
  B. a life cycle
  C. Development Plan
  D. a critical path
  E. Management Plan
  ANS: B
  
  245. Which of the following time robbers end up creating additional work for the project manager and the project office?
  A. Failure to delegate
  B. Changes without notification or direction
  C. Unreasonable time constraints
  D. Over directing people
  E. All of the above
  ANS: E
  
  246. You are giving your team instructions on how to perform a new test which is different from the way that the team had performed it previously.
  The best way to verify that the learn understands what you want is to:
  A. obtain feedback
  B. analyze the team's perceptions barriers
  C. uses gestures in presenting the instructions
  D. analyze the team's decoding skills
  E. analyze the team's encoding skills
  ANS: A
  
  247. A common way by which executives provide the project manager with written authority is through:
  A. A common job description for all project managers
  B. An appointment letter
  C. A project charter
  D. All of the above
  E. B and C only
  ANS: E
  
  248. Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends
  approximately ______percent of his or her time communicating.
  A. 40-50
  B. 50-60
  C. 60-75
  D. 75-90
  E. 90-95
  ANS: D
  
  249. The Work Breakdown Structure (WBS) is the basis for communicating:
  A. Project scope, cost control, schedule, quality
  B. Project objectives, dependencies, plan, cost control
  C. Project scope, schedule, staffing, cost control
  D. Project scope, quality, schedule, dependencies
  E. Project budget, schedule, risk factors, work assignments.
  ANS: A
  
  250. The quality objectives are approved in the conceptual stage of the project by the:
  A. Project Engineer
  B. Project Manager
  C. Functional Manager
  D. Quality Assurance Manager
  E. Project Owner
  ANS: E
  
  251. Total Project Risk:
  A. should not be calculated for small projects
  B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the
  project.
  C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
  D. A and B
  E. A and C
  ANS: C
  
  252. _____ is a narrative description of the work to be accomplished or resource to be supplied.
  A. Purchase order
  B. Level of effort work
  C. Scope of work
  D. Contract stipulation
  E. None of the above.
  ANS: C
  
  253. A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks
  most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
  A. 4 weeks
  B. 5 weeks
  C. 6 weeks
  D. 7 weeks
  E. None of the above.
  ANS: B
  
  254. In Project Risk Management, Risk Response may include actions to:
  A. reduce the probability of risk events
  B. change the scope, budget, schedule or quality specifications of the project
  C. reduce the consequences or severity of impacts of a potential risk event
  D. A and C
  E. All of the above.
  ANS: E
  
  255. Researching, organizing and recording pertinent information is called:
  A. Alternative analysis
  B. Information gathering
  C. Configuration management
  D. Post project analysis
  E. All of the above
  ANS: B
  
  256. The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.
  A. Unauditable.
  B. Undistributed.
  C. Preauthorized.
  D. Contingency.
  E. In-process.
  ANS: B
  
  257. The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a
  good start at team building by providing the team with:
  A. Proposed salary increases if the project is successful
  B. Bonuses for early completion date
  C. A promise of future assignments
  D. Well-defined project objectives
  E. Linear responsibility charts
  ANS: D
  
  258. To determine whether or not the employee correctly understands the message, the project manager needs to:
  A. reduce the filtering
  B. eliminate barriers
  C. obtain feedback
  D. use more than one medium
  E. use all of the above.
  ANS: C
  
  259. What is the relative priority of project Cost, Schedule and Quality?
  A. 1)Cost - 2)Schedule - 3)Quality
  B. 1)Quality - 2)Schedule - 3)Cost
  C. 1)Quality - 2)Cost - 3)Schedule
  D. 1)Schedule - 2)Quality - 3)Cost
  E. All are of equal priority
  ANS: E
  
  260. _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.
  A. Acquisition
  B. Contract negotiation
  C. Procurement
  D. Purchase negotiation
  E. None of the above.
  ANS: B
  
  